Set task dependencies in a project
Updated
Who can do this: Super Admins, Creators, Collaborators and Integrators, and Contributors on projects they're members of
A task dependency makes a task wait for other tasks. The waiting task shows Blocked until every task it's blocked by is complete. Work order settings on its module can keep it blocked after that, as described in How blocking works.
Before you begin
The tasks you want to link must already exist in the project.
Add a dependency
Go to Projects and open the project.
Select the task you want to link. It opens in a side panel on its Details tab.
Under Dependencies, select Add Dependency. A new row appears with two dropdowns.
In the first dropdown, choose the type:
Blocked By (the default): this task waits for the task you pick.
Blocks: the task you pick waits for this task.
In the second dropdown, choose the task. Tasks are grouped by module, and you can search by name.
The dependency saves as soon as you choose a task. To make a task wait on more than one task, repeat steps 3 to 5. It stays Blocked until all of them are complete.
The picker lists the project's other tasks that aren't already linked on another row, so you can link tasks in different modules. It leaves out the task you're editing. When the type is Blocked By, the row shows the chosen task's current status. To open the linked task, select the arrow button on its row.
How blocking works
A task that's already complete isn't moved back to Blocked when you add a dependency.
A blocked task can't be worked on or completed until the tasks it depends on are finished.
Work order settings on a module can also keep a task blocked after its dependencies are met.
For more on what each status means, see How task statuses work.
Change or remove a dependency
To change a dependency, choose a different type or task on its row. The change saves in place.
To remove a dependency, select the trash icon on its row, then select Delete Dependency.
Find what's blocking a task
Open the blocked task.
Select the Subtasks & Responses tab. It lists the tasks blocking this one.
Optional: To review them, select See Dependencies. It takes you to Dependencies on the Details tab. Automated tasks don't show this button.
You can also check Dependencies on the Details tab, which shows the status of each Blocked By task.
See dependencies on the Gantt chart
In the project, select the Gantt tab. Lines connect linked tasks, and the Dependencies column shows how many dependencies each task has. For more, see Using the project Gantt chart.
Set dependencies in a playbook or module
Playbook tasks and Library module tasks have the same Dependencies section in their task panel. Set dependencies there, and every project built from them starts with that order already set.