Project dates and task scheduling
Updated
Every project has a Start Date and an End Date. When you create a project from a playbook, you pick either date, and the other is set from the playbook's length. Task dates are scheduled from the project's start or end.
Some of what follows depends on automatic dates. This feature is available when it's turned on for your organization. If you don't see it, contact your OnRamp team.
How it works
Start date
You pick the Start Date when you create a project. Tasks scheduled from the project start count their dates forward from it.
End date
Without automatic dates, the end date comes from the playbook's latest task date. Tasks scheduled from the project end count their dates backward from it.
With automatic dates turned on for the playbook, the playbook's target length sets the end date if it has one. If it doesn't, the end date follows how long the tasks take.
Task dates
Without automatic dates, a task has a start date and a due date, each set as a number of days after project start or before project end. For example, a due date of 10 days after project start, or 2 days before project end. Tasks don't have durations. This lets one playbook fit projects of different lengths.
With automatic dates, a task date follows a rule instead. The rule counts days or business days before or after something it follows:
The project's start or end
Another task being done, starting, or reaching its start or due date
A form answer
A date data field
A date with no rule of its own can follow the task's other date and keep the task's length.
Change dates in a project
Change the end date
If the project still has open tasks, changing the End Date opens the Push date through all tasks dialog:
Push dates forward (or Push dates back) moves the due dates of all open tasks by the same number of days.
Maintain Current keeps them where they are. Some tasks can then fall after the project's end date.
With automatic dates, selecting the End Date lets you choose what sets it:
The last task's due date changes when task dates change.
A date you pick stays where you put it. The Target shows beside the Projected end, with a note when the work ends before or after the target.
When the choices open in a pop-up, select Save. In the project's date panel, each choice saves as soon as you make it. Picking a date can still open the Push date through all tasks dialog.
Change task dates
To change one task, edit its start or due date in the project's task list. You can also drag and resize tasks in the Gantt chart, if you can edit the project's tasks and the project isn't in an end state, such as completed. Using the project Gantt chart covers this in detail.
In the Gantt chart, a task with only a start or a due date shows as a single-day item. A task with no date shows on the project end date.
With automatic dates, resetting a task can move the dates of tasks that follow it. See Reset a task in OnRamp.
Automatic dates in a project
When automatic dates is turned on for your organization, people who can update the project's status see an Automatic dates toggle in the project's settings. With it on, task dates follow other work and move as the project runs. With it off, every date stays where it was set.
Each task date shows a label that tells you where it came from:
Label | What it means |
|---|---|
Follows a rule | The date follows its rule and moves on its own. |
Estimate | The date is waiting on another task. It can show that the other task is late. |
Waiting | The date stays put until the date it follows is known. |
Set by hand | Someone edited the date. Its rule is paused. |
Moved by Aero | Aero moved it to when the task should finish, based on past projects. |
Aero move undone | Aero's move was undone. Aero won't move it again unless someone changes it. |
Set date | The date changes only when someone edits it. |
Overdue tasks and reminders
A task that passes its due date without being completed is marked Overdue. Overdue tasks show in the Gantt chart. The project's task list has an Overdue column, which is hidden until you show it. To list only overdue tasks, select Only show overdue in the filters on the Tasks page.
Due dates also time the Upcoming Task Reminder and the Overdue Task Reminder, when those are turned on in an account's notification settings.
Compare scheduled and actual dates
To see how tasks finish against their due dates, go to Insights > Performance > Task Performance. The report shows early, on-time and late tasks, the average variance, and the number of instances. With automatic dates, it also shows Finished by original due date. Contributors can't open it. See Core Insights: Task Performance.